Bow Ridge Field Investigation & Design

BowRidgeField-01

DESCRIPTION

Identify the source of spring water flowing into park area and develop a drainage design to mitigate the water away from the playing field and into the stormwater drainage system.

LOCATION

Bow Ridge Ball Diamond, 222M George Fox Trail

UPDATES

  • Consultant has been hired to perform groundwater monitoring program and provide detailed design for construction of drainage system.  

SCHEDULE

  • Installation of standpipes late March 2021
  • Groundwater monitoring program through September 2021
  • Detailed design delivered in fall of 2021.  

BACKGROUND

The spring flow in the south west portion of the Bow Ridge Sport Field has increased steadily in size for the past several years. The flow has reached a point where current runoffs are encroaching into the field of play on the baseball diamond.

BUDGET

Total project budget: $45,000

HOW WILL THIS PROJECT BENEFIT THE COMMUNITY?

Maintenance of parks and pathways, providing community connectivity and accessibility.

Updated on Mar 12, 2021