Construction updates

*Dates for all outdoor projects are weather-dependent. For your safety and the safety of the crews working, be patient, follow flag person directions and obey all barricades and signs. 

TimelineLocationDescription
September 19Cochrane Ranche

Historic Ranche & Glenbow Pathway Improvement

Paving preparation is currently in progress on the Cochrane Ranche section of the pathway improvement project. Although there will be some temporary pathway closures, weโ€™re committed to minimizing disruptions so you can continue to enjoy the beauty of Cochrane Ranche. 

September 19 - October 3River Heights Drive/Riviera Way

Temporary lane closure

Temporary lane closures will occur on Riviera Way and River Heights Drive for concrete work. Please follow the instructions from signs and flaggers. 

September 17Fourth Avenue wall 

Cochrane wall enhancement installation 

The strucural components have been installed, and the wall enhancements are going up this week on the 4th Avenue retaining wall. 

To minimize disruptions, work will be scheduled outside of school drop-off and pick-up times.

Please be aware that temporary lane closures and detours may occur at various stages of the project.

September 10Highway 1A/22 Interchange

Highway 1A/22 Interchange update:

Alberta Transportation and Economic Corridors advises that a major traffic shift will occur this week as part of the Hwy 1A/22 interchange project.


The shift will begin the evening of Wednesday, September 11, and be completed overnight, with new lanes open for the Thursday morning commute. Traffic on Highway 22 will move to new pavement north of the temporary roundabout, rejoining the existing pavement near Ranche Road. The connection to the roundabout will change, and drivers should proceed with caution. A new ramp from westbound Highway 1A to northbound Highway 22 will also open, allowing traffic to bypass the temporary roundabout. The shift will happen in stages overnight, with brief traffic stoppages, and new signage will be in place to guide drivers. Closed sections of old pavement will be removed following the shift. Please drive carefully and be mindful of the new traffic setup.

highway 1a/22 traffic shift

 

We appreciate residentsโ€™ continued patience as this important project progresses. Please contact hwy1a22@islengineering.com if you have any questions.

More information: https://www.alberta.ca/cochrane-interchange.aspx

August 26 - September 30River Heights Drive - Rivercrest 

River Heights Drive & Rivercrest Traffic Light Installation

Traffic flow on River Heights Drive will be reduced to one lane in each direction to accommodate a new traffic light installation. Please follow all signage and direction from crews.

Aerial view of the intersection and detours

 

Summer-Fall 2024Highway 1A/22

๐—”๐—น๐—ฏ๐—ฒ๐—ฟ๐˜๐—ฎ ๐—ง๐—ฟ๐—ฎ๐—ป๐˜€๐—ฝ๐—ผ๐—ฟ๐˜๐—ฎ๐˜๐—ถ๐—ผ๐—ป ๐—›๐—ถ๐—ด๐—ต๐˜„๐—ฎ๐˜† ๐Ÿญ๐—”/๐Ÿฎ๐Ÿฎ ๐—œ๐—ป๐˜๐—ฒ๐—ฟ๐—ฐ๐—ต๐—ฎ๐—ป๐—ด๐—ฒ ๐—จ๐—ฝ๐—ฑ๐—ฎ๐˜๐—ฒ

Crews will be hauling material across both the east and south legs of the detour roundabout and continue throughout the summer. Crossings are flagger controlled. Additionally, crews will be hauling material across both the west and occasionally the south legs of the detour roundabout and will continue this into the fall. Crossings are flagger controlled. 

July - OctoberGlenbow Pathway

Historic Ranche & Glenbow Pathway Improvement

Construction is underway and temporary pathway closures have been established.